Mill Road – Granville Project

ATC will build a new substation in the village of Menomonee Falls, construct a new power line from Menomonee Falls to Wauwatosa, and rebuild and upgrade several existing lines in portions of Milwaukee, Washington and Waukesha counties.

The key elements of the project include:

  • Building a new Mill Road Substation on property ATC currently owns in the village of Menomonee Falls near Mill and Marcy Roads.  
  • Constructing a new 138-kilovolt power line from the new Mill Road Substation to the existing Butler Substation in Wauwatosa. The Public Service Commission of Wisconsin authorized the primary route for this new line. 
  • Rebuilding power lines running from the new Mill Road Substation to an existing substation along 76th Street in Milwaukee. Upgrading the voltage on one of the lines from 138-kV to 345-kV. During construction, a temporary 138-kV line will be installed on the south side of our existing lines for approximately one mile from the new Mill Road Substation to the existing substation east of Marcy Road. 
  • Replacing conductor wires on the existing power lines running north from the new Mill Road Substation to an existing substation in the village of Germantown. Certain structures (poles) will also be replaced. 
  • Make some upgrades to the line running south of the new Mill Road Substation south to an existing substation in New Berlin. Some structures (poles) may be replaced to bring the power line up to standards. 

The project is estimated to cost approximately $400 million.

The project is needed to maintain reliability and support local energy demand. Additional information about the project can be found on the Public Service Commission of Wisconsin website, under docket number 137-CE-212.

Project Video

Milestones

October 2024

The application was submitted to the PSCW.

Late 2025

The application was verbally approved by the PSCW. ATC is expecting a final written order from the PSCW in the coming weeks.

Summer 2026

Project construction is anticipated to begin.

Fall 2027

Project is anticipated to be in service.

October 2024

The application was submitted to the PSCW.

*Dates are anticipated and subject to changes
Late 2025

The application was verbally approved by the PSCW. ATC is expecting a final written order from the PSCW in the coming weeks.

*Dates are anticipated and subject to changes
Summer 2026

Project construction is anticipated to begin.

*Dates are anticipated and subject to changes
Fall 2027

Project is anticipated to be in service.

*Dates are anticipated and subject to changes

Project FAQ's

A:

The project is needed to maintain reliability and support local energy demand.

A:

ATC is constructing a new 138-kV power line from the new Mill Road Substation to the existing Butler Substation in Wauwatosa. ATC was required to propose two route alternatives for this new line, and the Public Service Commission of Wisconsin approved our project and authorized the primary route

A:

We anticipate the cost of the projects will be approximately $400 million. The cost of the project would be shared by all ATC customers.